Evotel maintenance Eden Terrace (In Progress)
  • Priority - Critical
  • Affecting Other - Evotel
  • Please note that Evotel maintenance teams are working on pulling a new cable and re splicing
    at Eden Terrace today so there is down time expected from 08:00 until 13:00 today (14/01/2019).

  • Date - 14/01/2019 08:00 - 14/01/2019 13:00
  • Last Updated - 14/01/2019 08:27
#578 (Scheduled)
  • Priority - Critical
  • Affecting Other - Vumatel - Active Ethernet
  • Good Day,

    Please be advised of the following emergency change.

    Change Reference: #578
    Start Date: 26 October 2018 @ 00h01
    End Date: 26 October 2018 @ 07h00
    Area/s Affected: Linden [LD-AG7]
    Network Type Affected: Active Ethernet
    Change Description: Re-do the dome joint to stabilise the fibre service
    Change Impact: Residents will have no connectivity during this time

  • Date - 26/10/2018 00:01 - 26/10/2018 07:00
  • Last Updated - 26/10/2018 07:02
Vumatel #564 (Scheduled)
  • Priority - High
  • Affecting Other - Maintenance
  • Change Reference:

    #564

    Start Date:

    24 October 2018 @ 08h00

    End Date:

    25 October 2018 @ 18h00

    Area/s Affected:

    Greenside - VT-GS-B007

    Network Type Affected:

    Active Ethernet

    Change Description:

    Resplice dome joint to stabilise the fibre service

    Change Impact:

    Residents will experience intermittent connectivity from 08h00 to 17h00 on these days

  • Date - 24/10/2018 00:00 - 25/10/2018 00:00
  • Last Updated - 22/10/2018 10:21
Vumatel #563 (Scheduled)
  • Priority - High
  • Affecting Other - Maintenance
  • Change Reference:

    #563

    Start Date:

    23 October 2018

    End Date:

    31 October 2018

    Note:

    The change window excludes the 27th & 28th of October

    Area/s Affected:

    Lanzerote MDU |Northriding

    Network Type Affected:

    Aerial

    Change Description:

    Replacing all central termination points in the MDU and resplice the fibres

    Change Impact:

    Residents will experience intermittent connectivity from 08h00 to 16h00 on these days

  • Date - 23/10/2018 00:00 - 31/10/2018 00:00
  • Last Updated - 22/10/2018 10:20
Vumatel #562 (Scheduled)
  • Priority - High
  • Affecting Other - Maintenance
  • Change Reference:

    #562

    Start Date:

    23 October 2018

    End Date:

    24 October 2018

    Area/s Affected:

    Ferndale

    Network Type Affected:

    Aerial

    Change Description:

    Re-routing of patch leads to manage slack and general preventative maintenance

    Change Impact:

    Residents will experience intermittent connectivity from 08h00 to 16h00 on these days

     

  • Date - 23/10/2018 00:00 - 24/10/2018 00:00
  • Last Updated - 22/10/2018 10:18
Vumatel #527 (Scheduled)
  • Priority - Critical
  • Affecting Other - Suspected Fibre Break
  • Network Incident Reference:

    #527

    Current Status

    Technicians will only be able to get access and attend at 06:00 a.m. tomorrow (08/10/2018), as this is a complex

    Area/s Affected:

    Le Club MDU

    Network Type Affected:

    GPON

    Network Incident Description:

    Suspected Fibre break

    Network Incident Impact:

    Residents will have no connectivity

  • Date - 08/10/2018 06:00
  • Last Updated - 08/10/2018 09:04